You are the manager of a major portfolio with a variety of stakeholders and stakeholder groups. you know that managing communication is key to success and you stress on maintaining a high communication level. You have just finalized the development of the Portfolio Communication Management Plan. Which of the following is correct regarding its purpose and focus?

Show Suggested Answer Hide Answer
Suggested Answer: C

The Portfolio Communication Management Plan defines all communication needs, establishes communication requirements, specifies frequency, and identifies recipients for information associated with the portfolio management process


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel