As soon as you complete the portfolio risk management plan, and you have been working on it now with a team, you realize you need to update some organizational process assets such as:
Haha, I'm just glad they didn't ask us to update the risk checklists. Those things are a nightmare to keep current! But yeah, I'm with Candra and Mose on this one - lessons learned is the way to go.
You know, I was leaning towards B) Risk register. Keeping that updated is critical for ongoing risk management, right? But I can see the value in documenting lessons learned as well. This is a tough call.
I agree with Candra. Updating the lessons learned repository is super important. That way, the next team that takes on a similar project can benefit from our experiences, both good and bad.
Hmm, this is a tricky one. I think the answer is C) Lessons learned. We've been working hard on this portfolio risk management plan, and as we wrap it up, I think it's crucial that we document any key lessons or insights we gained along the way.
Leonida
8 months agoCristy
8 months agoXenia
8 months agoRoy
8 months agoMichael
8 months agoMarguerita
8 months agoDerick
8 months agoOretha
9 months agoRessie
10 months agoMarsha
11 months agoGoldie
11 months agoMose
11 months agoCandra
11 months agoAntonio
10 months agoLatanya
10 months agoEvette
10 months agoAnthony
10 months agoViola
10 months agoBulah
10 months ago