As soon as you complete the portfolio risk management plan, and you have been working on it now with a team, you realize you need to update some organizational process assets such as:
Haha, I'm just glad they didn't ask us to update the risk checklists. Those things are a nightmare to keep current! But yeah, I'm with Candra and Mose on this one - lessons learned is the way to go.
You know, I was leaning towards B) Risk register. Keeping that updated is critical for ongoing risk management, right? But I can see the value in documenting lessons learned as well. This is a tough call.
I agree with Candra. Updating the lessons learned repository is super important. That way, the next team that takes on a similar project can benefit from our experiences, both good and bad.
Hmm, this is a tricky one. I think the answer is C) Lessons learned. We've been working hard on this portfolio risk management plan, and as we wrap it up, I think it's crucial that we document any key lessons or insights we gained along the way.
Leonida
5 months agoCristy
5 months agoXenia
6 months agoRoy
6 months agoMichael
6 months agoMarguerita
6 months agoDerick
6 months agoOretha
6 months agoRessie
7 months agoMarsha
8 months agoGoldie
8 months agoMose
8 months agoCandra
8 months agoAntonio
8 months agoLatanya
8 months agoEvette
8 months agoAnthony
8 months agoViola
8 months agoBulah
8 months ago