BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam CAPM Topic 5 Question 72 Discussion

Actual exam question for PMI's CAPM exam
Question #: 72
Topic #: 5
[All CAPM Questions]

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Luisa
6 months ago
Oh, I get it now. Thanks for that breakdown!
upvoted 0 times
...
Alishia
6 months ago
So, (2 + 4*4 + 6) / 6 = 4 days. C seems correct.
upvoted 0 times
...
Izetta
6 months ago
Right, Optimistic (2), Most Likely (4), Pessimistic (6).
upvoted 0 times
...
Audrie
6 months ago
I think it’s straightforward. The formula is (O + 4M + P) / 6, right?
upvoted 0 times
...
Alishia
6 months ago
Yeah, the three-point estimating technique can be confusing.
upvoted 0 times
...
Luisa
6 months ago
Anyone else find that question tricky?
upvoted 0 times
...

Save Cancel