Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam CAPM Topic 4 Question 58 Discussion

Actual exam question for PMI's CAPM exam
Question #: 58
Topic #: 4
[All CAPM Questions]

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel