BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam CAPM Topic 4 Question 13 Discussion

Actual exam question for PMI's CAPM exam
Question #: 13
Topic #: 4
[All CAPM Questions]

A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel