Which is consistent with the eight guidance points of PRINCE2 Agile?
This highlights that while Scrum and Kanban have their own roles and frameworks, the role of the project manager can still exist and be integrated within Agile practices, including PRINCE2 Agile.
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team has created a plan of 9 timeboxes that always end on a Friday. The senior user has decided to visit the Marketing Team every Friday in order to attend their regular reviews.
Which reason BEST explains whether this is a suitable approach for the 'directing a project' process?
Regular reviews conducted by the senior user allow for continuous assessment of the project's progress, ensuring that the project remains aligned with its objectives and can adapt to any necessary changes. This ongoing engagement is vital for maintaining project viability and stakeholder involvement.
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
A requirement for the changing room facilities in the Event Village has been defined as a technical story as follows:
'Changing room facilities should have water pressure between 1.5 - 3 bar and must have a water pressure of at least between 0.1 - 0.5 bar.'
Has this requirement been recorded correctly?
Non-functional requirements, such as performance criteria (in this case, water pressure), should typically be included as part of the user stories to ensure they are considered in the context of the overall functionality and user experience. This integration helps maintain a holistic view of what the system should deliver, ensuring that both functional and non-functional aspects are addressed together.
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
Just before the event the team finds out that a major football match is taking place during the tournament and that many people will want to see it. One solution is to hire a large TV screen to display the game in the Event Village. However, the biggest concern is that the cheapest supplier has many mandatory requirements for access, technical elements and work conditions in their contract.
If the agile environment for the project was reassessed, should the 'Advantageous Environmental Conditions' slider on the Agilometer be increased?
If the supplier has many mandatory requirements for access, technical elements, and work conditions that may hinder flexibility and responsiveness, it suggests that the conditions are not conducive to an agile environment. This lack of support for agile principles would warrant a reduction in the 'Advantageous Environmental Conditions' slider on the Agilometer.
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team is not sure whether all the information, photos and links needed for the website pages being set up by the Website Team can be delivered within the current timebox.
One of the team members has suggested that the team regularly visit the LGA's cafeteria to show the staff in other departments some rough drawings of the website pages to get their feedback. This can then be used to help decide which parts of each page are most important to deliver within the timebox.
Which BEST explains how this approach manages change?
By seeking feedback from staff on rough drawings of the website pages, the Marketing Team can make informed decisions about what content is most valuable and should be prioritized for delivery within the current timebox. This responsive approach allows the team to adapt to feedback effectively, ensuring the final product meets stakeholder needs.
Wendell
4 days agoTamekia
14 days agoLorrie
29 days agoKrissy
1 months agoMalcolm
1 months agoLenna
2 months agoNgoc
2 months agoStephaine
2 months agoNguyet
3 months agoClorinda
3 months agoBo
3 months agoKeneth
3 months agoLauran
4 months agoLawanda
4 months agoMatt
4 months agoMerlyn
4 months agoAnnita
4 months agoMilly
4 months agoMilly
5 months agoPhuong
5 months agoRaul
5 months ago