PeopleCert Exam ITIL-4-Foundation Topic 3 Question 62 Discussion

Actual exam question for PeopleCert's ITIL-4-Foundation exam
Question #: 62
Topic #: 3
[All ITIL-4-Foundation Questions]

What can a change schedule be used for?

Show Suggested Answer Hide Answer
Suggested Answer: B

The change schedule is used tohelp plan changes, assist in communication, avoid conflicts, and assign resources. It can also be used after changes have been deployed to provide information needed for incident management, problem management, and improvement planning

https://www.bmc.com/blogs/itil-change-enablement/#:~:text=The%20change%20schedule%20is%20used,problem%20management%2C%20and%20improvement%20planning.