PeopleCert Exam 299 Topic 2 Question 49 Discussion

Actual exam question for PeopleCert's 299 exam
Question #: 49
Topic #: 2
[All 299 Questions]

Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Selma
6 months ago
I believe those roles are more about monitoring and supporting the project overall, not specifically responding to risks.
upvoted 0 times
...
Nu
6 months ago
But what about Project Assurance or Project Support?
upvoted 0 times
...
Ligia
6 months ago
I agree, the risk owner is the one responsible for taking action on a risk.
upvoted 0 times
...
Ciara
6 months ago
I think the missing word is D) the risk owner.
upvoted 0 times
...
Sommer
7 months ago
Hmm, I don't know. Project Support sounds more like a general support role, not the specific person responsible for the risk response. I think C is still the best fit here.
upvoted 0 times
...
Nakisha
7 months ago
You know, I was also considering B, 'Project Support'. Isn't that the team that helps coordinate risk responses and other project activities? Maybe they could be considered responsible for carrying out the risk actions.
upvoted 0 times
...
Leah
7 months ago
That's a good point, but I think the risk owner is more responsible for the overall risk management process, while the risk actionee is the one who actually implements the risk response. C just seems to fit the description better.
upvoted 0 times
...
Shaniqua
7 months ago
Hmm, I was leaning towards D, 'the risk owner'. Isn't the risk owner the one who's accountable for managing the risk and ensuring the response is carried out?
upvoted 0 times
...
Devorah
7 months ago
I agree, C seems like the correct answer. The risk owner is the one who's responsible for the risk, but the risk actionee is the one who does the work to address it.
upvoted 0 times
Kathrine
6 months ago
I would go with C) the risk actionee.
upvoted 0 times
...
Coral
6 months ago
I think it's D) the risk owner.
upvoted 0 times
...
...
Mike
7 months ago
This question is testing our knowledge of risk management terminology. I think the answer is C, 'the risk actionee'. That's the person responsible for actually carrying out the risk response action.
upvoted 0 times
...