PECB Exam ISO-IEC-20000-Foundation Topic 2 Question 5 Discussion

Actual exam question for PECB's ISO/IEC 20000 Foundation Exam exam
Question #: 5
Topic #: 2
[All ISO/IEC 20000 Foundation Exam Questions]

One of the activities required for effective planning, coordination, and evaluation of requested changes is assessing the impact and required resources. Which process or function is responsible for this activity?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Francene
4 days ago
Change management, hands down. They're like the traffic cops of the IT world, making sure everything flows smoothly.
upvoted 0 times
...
Sherita
9 days ago
I believe the correct answer is C) Change management because it is specifically focused on managing changes and their impact on resources.
upvoted 0 times
...
Dierdre
11 days ago
Hmm, this is a tricky one. I'm gonna go with Service desk, because they're the ones who field all the change requests in the first place.
upvoted 0 times
...
Galen
13 days ago
Oh, this is an easy one. It's gotta be Release and deployment management. They're the ones who make the magic happen!
upvoted 0 times
...
Avery
13 days ago
I'm going with Configuration management on this one. They're the real MVPs when it comes to keeping track of all the moving parts.
upvoted 0 times
Ressie
7 days ago
I think Configuration management is the right choice too. They really keep everything organized.
upvoted 0 times
...
...
Edwin
22 days ago
I'm not sure, but I think it could also be D) Configuration management.
upvoted 0 times
...
Ronna
29 days ago
Change management, for sure! They're the ones who have to make sure the impact and resources are all accounted for.
upvoted 0 times
Rebecka
13 days ago
I agree, change management is definitely responsible for assessing the impact and required resources.
upvoted 0 times
...
Venita
13 days ago
Yes, change management plays a crucial role in ensuring that all aspects of a requested change are properly evaluated.
upvoted 0 times
...
...
Cora
1 months ago
I agree with Marcelle, Change management is responsible for assessing the impact and required resources.
upvoted 0 times
...
Marcelle
1 months ago
I think the answer is C) Change management.
upvoted 0 times
...