Question #: 8
Topic #: 3
[All ISO-22301-Lead-Auditor Questions]

The purpose of risk management for business continuity is to find out what problems an organization may face.

How should the level of risk for an organization be determined?

Show Suggested Answer Hide Answer
Suggested Answer: A