Oracle Exam 1Z0-1075-24 Topic 1 Question 16 Discussion

Actual exam question for Oracle's 1Z0-1075-24 exam
Question #: 16
Topic #: 1
[All 1Z0-1075-24 Questions]

Which statement is NOT true about cumulative lead time?

Show Suggested Answer Hide Answer
Suggested Answer: D

Cumulative lead time is a key concept in Oracle Manufacturing Cloud, where it calculates the total time required to manufacture an item. The following points clarify the calculations:

Statement D is incorrect because cumulative lead time does not update the lead time percent at the operation level in the work definition. Instead, cumulative lead time focuses on rolling up the lead times of both make and buy items to provide an overall lead time for the entire production process.

Correct Statements:

Statement A: The system calculates cumulative manufacturing lead time by summing up the lead times of all make items in the production process.

Statement B: At the end of the cumulative lead time calculation process, it updates the lead time attributes of the item, specifically cumulative manufacturing and cumulative total lead times.

Statement C: Cumulative total lead time includes both make and buy item lead times, representing the complete production cycle from procurement to manufacturing.


Contribute your Thoughts:

Melvin
2 months ago
Haha, lead time percent at the operation level? What kind of crazy question is this? I'm going with option C, it seems the most comprehensive description of cumulative lead time.
upvoted 0 times
...
Miesha
2 months ago
But D talks about updating lead time percent, not cumulative lead time.
upvoted 0 times
...
Theron
2 months ago
Option B seems correct to me. Updating the item's lead time attributes is definitely part of the cumulative lead time calculation process.
upvoted 0 times
Marva
7 days ago
That's a good point, option A is definitely not true about cumulative lead time.
upvoted 0 times
...
Lauran
8 days ago
Option A is also incorrect because it calculates cumulative manufacturing lead times, not just lead times of make items.
upvoted 0 times
...
Jean
17 days ago
I agree with you, option D makes sense in the context of cumulative lead time calculation.
upvoted 0 times
...
Ramonita
1 months ago
I think option D is the correct answer. It updates lead time percent at the operation level in the work definition.
upvoted 0 times
...
...
Laura
2 months ago
I disagree, I believe the answer is C.
upvoted 0 times
...
Judy
2 months ago
I think option D is not true. The question specifically asks about cumulative lead time, and I don't think lead time percent at the operation level is part of that calculation.
upvoted 0 times
Theresia
1 months ago
Yes, I think option D is the odd one out here.
upvoted 0 times
...
Selene
2 months ago
I agree, option D seems unrelated to cumulative lead time calculation.
upvoted 0 times
...
...
Miesha
2 months ago
I think the answer is D.
upvoted 0 times
...