Which precedence order is used by the system for labor schedules to distribute payroll cost?
The precedence order that is used by the system for labor schedules to distribute payroll cost is Assignment > Assignment Element > Element. This means that the system first looks for a labor schedule that is assigned to the employee assignment, then for a labor schedule that is assigned to the payroll element of the employee assignment, and finally for a labor schedule that is assigned to the payroll element itself. The system uses the first labor schedule that it finds in this order to distribute the payroll cost to projects and tasks based on the hours and rates defined in the schedule. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2356121