A customer has these requirements for their proposed Data Guard implementation:

1. Zero data loss must still be guaranteed through the loss of any one configuration component.

2. The primary database must be protected against a regional disaster.

3. Performance overheads on the primary should be minimized as much as possible given these requirements.

4. Downtime on the primary database for any reason must be kept to a minimum.

Components referred to in the broker commands are:

A)

B)

C)

D)

Show Suggested Answer Hide Answer
Suggested Answer: A, B, C, E

The rate of SQL apply on a logical standby database can be influenced by:

A: The number of PREPARER processes (which seems to be a typographical error and should read as PREPARER or similar) which prepare the redo data for the applier processes.

B: The number of coordinator processes on the standby database instance which coordinate the SQL apply activities.

C: The number of full table scans performed by SQL apply since full table scans can be resource-intensive and slow down the apply rate.

E: The number of applier processes which apply the redo data to the logical standby database.

Option D is incorrect as the size of the undo tablespace on the logical standby database is more likely to affect the SQL apply lag rather than the rate of SQL apply.

Option F is incorrect because the size of the shared pool would typically not influence the rate of SQL apply. The shared pool is more related to the caching of shared SQL and PL/SQL code and control structures.