Refer to the exhibit.

In the execution of the Scatter-Gather, the "steep 1 sec" Flow Reference takes about 1 second to complete, and the "sleep 5 sees" Row Reference takes about 5 seconds to complete.

About how many seconds does it take from the time the Scatter-Gather is called until the Set Payload transformer is called?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Jeniffer
5 months ago
I believe the answer is C) 5 seconds, considering the time taken by each step.
upvoted 0 times
...
Teresita
5 months ago
I'm not sure, but I think it might be B) 1 second.
upvoted 0 times
...
Eloisa
5 months ago
I agree with Glennis, because both the Flow Reference and Row Reference are executed in parallel.
upvoted 0 times
...
Glennis
5 months ago
I think the answer is A) 0 seconds.
upvoted 0 times
...
Alton
5 months ago
I think it's 0 seconds.
upvoted 0 times
...
Ashton
5 months ago
I agree with user 1, it definitely takes 6 seconds.
upvoted 0 times
...
Gilberto
6 months ago
No, I believe it only takes 1 second.
upvoted 0 times
...
Joanna
6 months ago
I think it takes 6 seconds.
upvoted 0 times
...
Lorenza
7 months ago
Okay, I think I've got it. The key here is that the Scatter-Gather runs the two references in parallel. So, the overall duration is determined by the longer of the two, which is 5 seconds. Therefore, the correct answer is C. *high-fives Darci* Nice work, team!
upvoted 0 times
Roosevelt
6 months ago
Charlie
upvoted 0 times
...
Laurel
6 months ago
Bob
upvoted 0 times
...
Luisa
6 months ago
Alice
upvoted 0 times
...
...
Curtis
7 months ago
I agree with Darci. The Scatter-Gather runs the two references in parallel, so the overall duration is determined by the longer one, which is 5 seconds. C is the correct answer.
upvoted 0 times
...
Darci
7 months ago
Hmm, this question is quite tricky. The way I see it, the 'steep 1 sec' Flow Reference and the 'sleep 5 sees' Row Reference run concurrently in the Scatter-Gather. So, the time it takes until the Set Payload transformer is called should be the maximum of these two durations, which is 5 seconds. I'm going with option C.
upvoted 0 times
...