BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft 70-348 Exam Questions

Status: RETIRED
Exam Name: Managing Projects and Portfolios with Microsoft PPM
Exam Code: 70-348
Related Certification(s): Microsoft Certified Professional MCP Certification
Certification Provider: Microsoft
Actual Exam Duration: 55 Minutes
Number of 70-348 practice questions in our database: 48 (updated: 05-02-2018)
Expected 70-348 Exam Topics, as suggested by Microsoft :
  • Topic 1: Build A Project Team Through Project Pro For Office 365 Or Project Web App/ Create Multiple Driver Prioritizations
  • Topic 2: Plan Program Financial Requirements Using The Resource Rate Table/ Rate Projects Against Business Drivers
  • Topic 3: Plan Resource Allocations Using Team Planner/ Set A Baseline From Project Web App And Project Pro For Office 365
  • Topic 4: Import Projects Through Project Professional/ Associate Programs To Portfolios/ Synchronize Deliverables With Project Effort-Driven Tasks, And Formulas/ Create A Project And Manage Workflow/ Determine Primary Cost Constraints
  • Topic 5: Create And Manage Project Schedules Using Project Web App/ Define Business Drivers/ Analyze Consistency Ratio Resolve Resource Over Allocations Across Projects/ Capture Project Requests And Ideas
  • Topic 6: Review And Modify Prioritizations In An Analysis/ Create Cross-Project Task Dependencies
  • Topic 7: Force Projects In And Out Of Analysis/ Calculate Sub-Project Summary Fields/ Determine Resource Constraints Submit, Accept, Modify, And Reject A Resource Engagement Request/ Create Manually Scheduled Tasks/ Set Tasks As Active Or Inactive Build A Project Team Through Project Web App/ Set The Published Values For Individual Tasks
  • Topic 8: Update Schedules With Protected User Updates/ Collaborate And Communicate Projects And Programs
  • Topic 9: View Impact Of Updates On A Project/ Create And Modify Summary Tasks And Subtasks
  • Topic 10: Reschedule Uncompleted Work/ Update Cost Resources, Set Project Dependencies, Create A Portfolio Analysis Edit Resources With Project Pro For Office 365/ Compare And Run Simulations For Project Portfolio Selection
  • Topic 11: Create Program (Master-Sub) Structure Using Subsites/ Use Committed Versus Proposed Assignments
  • Topic 12: Import Projects From Excel/ Determine Hired Resources/ Set Dependencies On Deliverables
  • Topic 13: Build A Resource Plan For A Project/ Create Tasks And A Work Breakdown Structure Accept Task Updates From Tasks Or Timesheets/ Approve Tasks And Timesheets/ Create A New Enterprise Project
  • Topic 14: Baseline Enterprise Projects/ Update Tasks And Timesheets/ Submit And Recall Timesheets
Disscuss Microsoft 70-348 Topics, Questions or Ask Anything Related

Currently there are no comments in this discussion, be the first to comment!

Free Microsoft 70-348 Exam Actual Questions

Note: Premium Questions for 70-348 were last updated On 05-02-2018 (see below)

Question #1

An organization uses Microsoft PPM to manage projects. The organization tracks all projects by collecting time on tasks on a daily basis.

You need to ensure that resources can enter their time on tasks.

Which three actions should you take? Each correct answer presents part of the solution.

Reveal Solution Hide Solution
Correct Answer: A, B, C

Question #2

You are a project manager for an organization that uses Microsoft PPM. You plan each project in phases.

Team members must only see the assignments from a selected phase. All reports and project schedule views must reflect the entire project schedule, so the entire project is visible to the management team.

You need to configure Microsoft PPM.

What should you do?

Reveal Solution Hide Solution
Correct Answer: D

Question #3

You are a project manager in an organization that uses Microsoft PPM.

You have been given additional responsibilities managing existing projects created by another project manager.

When reviewing the project plan, you observe that some of the upcoming tasks are assigned to a generic resource.

You need to update the generic tasks to use defined resources.

Which type of resource should you use?

Reveal Solution Hide Solution
Correct Answer: D

Question #4

This question requires that you evaluate the underlined text to determine if it is correct.

To review the resource engagements requested by a project manager, the resource manager can navigate to the Resource Requests page and accept or reject the requests.

Review the underlined text. If it makes the statement correct, select ''No change is needed.'' If the statement is incorrect, select the answer choice that makes the statement correct.

Reveal Solution Hide Solution
Question #5

You are an administrator for an organization that uses Microsoft PPM. A project manager is building a team for a project.

The project manager reports that a newly hired resource is not visible in Build Team.

You need to ensure that newly added users are available in Build Team.

What should you do?

Reveal Solution Hide Solution
Correct Answer: D


Unlock Premium 70-348 Exam Questions with Advanced Practice Test Features:
  • Select Question Types you want
  • Set your Desired Pass Percentage
  • Allocate Time (Hours : Minutes)
  • Create Multiple Practice tests with Limited Questions
  • Customer Support
Get Full Access Now

Save Cancel