BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft Exam MB-335 Topic 2 Question 18 Discussion

Actual exam question for Microsoft's MB-335 exam
Question #: 18
Topic #: 2
[All MB-335 Questions]

A company produces pipe at certain fixed lengths.

The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.

You need to configure the resources to account for these different products.

What should you do?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Rebbecca
5 months ago
I think creating a resource group for each length would also work. It helps in managing resources effectively.
upvoted 0 times
...
Mira
5 months ago
I think creating a resource for each length might be too rigid. Building capability seems more flexible.
upvoted 0 times
...
Sabra
6 months ago
What about creating a resource for each length? Wouldn't that be more specific?
upvoted 0 times
...
Julio
6 months ago
I agree with It makes sense to have the resources configured based on the different product lengths.
upvoted 0 times
...
Mira
6 months ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
Krissy
7 months ago
Or we could create a resource group for each length. That way we can manage them more efficiently.
upvoted 0 times
...
Abel
7 months ago
I don't think that's necessary. Creating a resource for each length might be more effective.
upvoted 0 times
...
Kerry
7 months ago
What about configuring the Data/Hour option on the Capacity unit field on the resource?
upvoted 0 times
...
Krissy
7 months ago
That sounds like a good idea. It would help us schedule the cutting machines better.
upvoted 0 times
...
Abel
7 months ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
Dominga
6 months ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
Reiko
6 months ago
D) Create a resource group for each length.
upvoted 0 times
...
Jess
6 months ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
...

Save Cancel