Microsoft Exam MB-335 Topic 2 Question 18 Discussion

Actual exam question for Microsoft's MB-335 exam
Question #: 18
Topic #: 2
[All MB-335 Questions]

A company produces pipe at certain fixed lengths.

The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.

You need to configure the resources to account for these different products.

What should you do?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Rebbecca
10 months ago
I think creating a resource group for each length would also work. It helps in managing resources effectively.
upvoted 0 times
...
Mira
10 months ago
I think creating a resource for each length might be too rigid. Building capability seems more flexible.
upvoted 0 times
...
Sabra
10 months ago
What about creating a resource for each length? Wouldn't that be more specific?
upvoted 0 times
...
Julio
11 months ago
I agree with It makes sense to have the resources configured based on the different product lengths.
upvoted 0 times
...
Mira
11 months ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
Krissy
11 months ago
Or we could create a resource group for each length. That way we can manage them more efficiently.
upvoted 0 times
...
Abel
11 months ago
I don't think that's necessary. Creating a resource for each length might be more effective.
upvoted 0 times
...
Kerry
11 months ago
What about configuring the Data/Hour option on the Capacity unit field on the resource?
upvoted 0 times
...
Krissy
11 months ago
That sounds like a good idea. It would help us schedule the cutting machines better.
upvoted 0 times
...
Abel
11 months ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
Dominga
11 months ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
Reiko
11 months ago
D) Create a resource group for each length.
upvoted 0 times
...
Jess
11 months ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
...