Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft Exam 74-343 Topic 1 Question 2 Discussion

Actual exam question for Microsoft's 74-343 exam
Question #: 2
Topic #: 1
[All 74-343 Questions]

You create a new schedule by using Microsoft Project. All calendars and working hours use default settings. You configure the schedule to show all assignment units as decimal values.

A resource reports a reduction in availability for your project by two hours per day.

You need to update the project to reflect the availability of the resource.

What are two possible ways to achieve the goal? Each correct answer presents a complete solution.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel