BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft Exam 74-343 Topic 1 Question 1 Discussion

Actual exam question for Microsoft's 74-343 exam
Question #: 1
Topic #: 1
[All 74-343 Questions]

You update a schedule that you are managing by using Microsoft Project.

After the update, you observe that many of the resources in the schedule are overallocated.

You need to resource level the schedule without changing the current projected finish data for the project.

Which three actions will achieve the goal? Each correct answer presents part of the solution.

Show Suggested Answer Hide Answer
Suggested Answer: B, C, E

References:

https://support.office.com/en-us/article/Level-resource-assignments-49fb52d5-ff4a-4b1f-b5c1-af057ab38ba2

http://www.dummies.com/software/microsoft-office/project/how-to-level-resources-in-project-2013/


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel