You update a schedule that you are managing by using Microsoft Project.
After the update, you observe that many of the resources in the schedule are overallocated.
You need to resource level the schedule without changing the current projected finish data for the project.
Which three actions will achieve the goal? Each correct answer presents part of the solution.
References:
https://support.office.com/en-us/article/Level-resource-assignments-49fb52d5-ff4a-4b1f-b5c1-af057ab38ba2
http://www.dummies.com/software/microsoft-office/project/how-to-level-resources-in-project-2013/