You are a project manager in an organization that uses Microsoft PPM.
You have been given additional responsibilities managing existing projects created by another project manager.
When reviewing the project plan, you observe that some of the upcoming tasks are assigned to a generic resource.
You need to update the generic tasks to use defined resources.
Which type of resource should you use?