When should component integration tests be carried out?
Component integration tests are designed to verify the interactions and interfaces between integrated components. These tests should be carried out after component testing (where individual components are tested in isolation) but before system testing (where the entire system is tested as a whole). This ensures that any issues arising from the integration of components are identified and resolved early in the testing process, making option D the correct answer.