Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

iSQI Exam CTFL_Syll2018 Topic 4 Question 104 Discussion

Actual exam question for iSQI's CTFL_Syll2018 exam
Question #: 104
Topic #: 4
[All CTFL_Syll2018 Questions]

Tests have been specified for the latest software release and users have prioritised these

However, there are some dependencies between tests as shown in the table below (e.g. Test ID. X cannot be run until Test ID. Y has been successfully completed).

Which test execution schedule best meets the prioritisation and dependency conditions?

Show Suggested Answer Hide Answer
Suggested Answer: D

The test execution schedule should follow the priority order of the tests, as well as the dependency constraints. The priority order is given by the user value column, where higher values indicate higher priority. The dependency constraints are given by the dependency column, where a test ID indicates that the test cannot be run until the test with that ID has been successfully completed. Therefore, the test execution schedule should start with the highest priority test that has no dependency, which is test 5. Then, it should continue with the next highest priority test that has no dependency or has a satisfied dependency, which is test 1. Then, it should proceed with test 2, which depends on test 1, and then test 3, which depends on test 2. Finally, it should end with test 4, which depends on test 3. Thus, the test execution schedule that best meets the prioritisation and dependency conditions is 5,1,2,3,4.


Contribute your Thoughts:

Sol
3 days ago
I'm not sure, but I think option D) 5,1,2,3,4 could also work.
upvoted 0 times
...
Wade
5 days ago
I agree with Novella, because it follows the prioritisation and dependency conditions.
upvoted 0 times
...
Magdalene
6 days ago
Hmm, I think the answer is C. It seems the most straightforward way to meet the dependencies.
upvoted 0 times
...
Novella
7 days ago
I think option C) 1,2,3,4,5 is the best schedule.
upvoted 0 times
...

Save Cancel