New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

iSQI Exam CTFL_Syll2018 Topic 1 Question 92 Discussion

Actual exam question for iSQI's CTFL_Syll2018 exam
Question #: 92
Topic #: 1
[All CTFL_Syll2018 Questions]

Which one of the following would you typically expect to find in a test completion report for a test level?

Show Suggested Answer Hide Answer
Suggested Answer: B

A test completion report for a test level typically includes a summary of all the testing activities that have been performed. It should detail any deviations from the original test schedule, including any changes in the planned duration or effort that were required to complete the test activities. This report serves as a record of what was tested, how it was tested, and any issues that were encountered.


Contribute your Thoughts:

Felix
4 months ago
As a test engineer, I'd expect to see a comprehensive summary in B). Anything less would be like a chef not tasting their own cooking - unacceptable!
upvoted 0 times
Tamekia
3 months ago
Reena: Without it, stakeholders wouldn't have a complete picture of the test activities.
upvoted 0 times
...
Reena
3 months ago
Definitely, it provides a clear overview of the testing performed.
upvoted 0 times
...
Marnie
3 months ago
I agree, B) is essential for a test completion report.
upvoted 0 times
...
...
Rosio
4 months ago
B) is the way to go. Who cares about the daily test plans or proposed approaches? I want the nitty-gritty details on how the testing went down, the good, the bad, and the ugly.
upvoted 0 times
Orville
3 months ago
B) is the way to go. Who cares about the daily test plans or proposed approaches? I want the nitty-gritty details on how the testing went down, the good, the bad, and the ugly.
upvoted 0 times
...
Arthur
3 months ago
B) A summary of the testing performed and any deviations from the schedule, duration or effort of test activities.
upvoted 0 times
...
Hildred
3 months ago
A) Factors that are currently impeding test progress and the tests planned for the following day.
upvoted 0 times
...
...
Melissia
4 months ago
Hmm, I'm torn between B and D. But I think B takes the cake - I need to know what actually happened, not just what was planned.
upvoted 0 times
Cyril
3 months ago
Definitely, it's important to have a summary of the testing performed and any deviations.
upvoted 0 times
...
Lavonda
3 months ago
I agree, knowing what actually happened is crucial for a test completion report.
upvoted 0 times
...
...
Chanel
4 months ago
I think both B and D are important in a test completion report.
upvoted 0 times
...
My
4 months ago
I believe it could also include D, the proposed exit criteria and metrics reports.
upvoted 0 times
...
Detra
5 months ago
I agree with Annett, a test completion report should include a summary of testing performed.
upvoted 0 times
...
Annett
5 months ago
I think the answer is B.
upvoted 0 times
...
Gabriele
5 months ago
I'd go with D. Stakeholders need to see the exit criteria and metrics to make sure the testing is on track, right? That's crucial for a test completion report.
upvoted 0 times
...
Arlette
5 months ago
Definitely B. Gotta love a report that gives me the juicy details on how the testing actually went down, not just the high-level plan.
upvoted 0 times
...
Margot
5 months ago
B) seems the most comprehensive option, covering both the testing performed and any deviations from the plan. That's exactly what I'd expect to see in a test completion report.
upvoted 0 times
Gerald
4 months ago
Option B is definitely the most detailed and informative choice for a test completion report.
upvoted 0 times
...
Lauran
4 months ago
Yes, it provides a good summary of the testing performed and any deviations from the schedule.
upvoted 0 times
...
Dorothy
4 months ago
I agree, option B covers all the necessary information in a test completion report.
upvoted 0 times
...
...

Save Cancel