Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

iSQI Exam CTFL_Syll_4.0 Topic 5 Question 30 Discussion

Actual exam question for iSQI's CTFL_Syll_4.0 exam
Question #: 30
Topic #: 5
[All CTFL_Syll_4.0 Questions]

Consider an estimation session where a six-member Agile team (Memb1, ... , Memb6) is performing a planning poker session to estimate a user story (in story points). Team

members are using a set of cards with the following values: 1, 2, 3, 5, 8, 13, 21. Below is the outcome produced by the first round of estimation for this session:

Which of the following answers best describes how the estimation session should proceed?

Show Suggested Answer Hide Answer
Suggested Answer: D

In Agile estimation sessions, particularly during Planning Poker, the goal is to reach a consensus on the effort required for a user story. The process encourages discussion and collaboration among team members to understand the story's requirements and complexities fully. Here's a breakdown of the options and why D is the correct choice:

Option A: Calculating the arithmetic mean of all estimates.

This method is straightforward but does not facilitate team discussion or consensus-building. It merely averages out the estimates without addressing the reasons behind the varying estimates. Thus, important insights and understanding of the task complexity might be missed.

Option B: Selecting the most frequent estimate value.

While this approach acknowledges the majority's opinion, it ignores the minority views, which might highlight significant aspects of the story that need consideration. It doesn't ensure that all perspectives are considered and discussed.

Option C: Calculating the mean of the most optimistic and pessimistic estimates.

This approach considers the extremes but again lacks the team discussion and consensus aspect. It also assumes that the extreme values alone can balance out the estimate, which might not always capture the true complexity or simplicity of the task.

Option D: Discussing the most pessimistic and optimistic estimates.

This approach fosters team collaboration and understanding. Memb4 and Memb6 explain their reasoning for the highest and lowest estimates, respectively, which can reveal different perspectives on the task's complexity. This discussion helps the team align their understanding and often leads to a more accurate and agreed-upon estimate in subsequent rounds.

In conclusion, the main goal of Agile estimation techniques like Planning Poker is to encourage team communication and collaboration to ensure that all aspects of the user story are considered. Option D best aligns with this goal by promoting discussion and consensus.


Contribute your Thoughts:

Daisy
13 days ago
21 story points? You're joking, right? I'm pretty sure I can do this in my sleep. Let's get real here, people.
upvoted 0 times
Marge
2 days ago
A) The final estimate of the user story in story points is determined as the arithmetic mean of all the estimates made by the team members during this first round, without the need to perform further rounds of estimation
upvoted 0 times
...
...
Felix
17 days ago
I went with 21 story points because this task looks like a real beast. Maybe I'm being too cautious, but I'd rather overestimate than underestimate.
upvoted 0 times
Elouise
8 days ago
I agree with you, it's better to overestimate than underestimate for such a complex task like this one.
upvoted 0 times
...
Dewitt
9 days ago
D) Memb4 and Memb6, which have produced the most pessimistic and the most optimistic estimates respectively, should explain the reasons of their choices to stimulate a discussion between all team members before to proceed to another round of estimation
upvoted 0 times
...
Fabiola
11 days ago
A) The final estimate of the user story in story points is determined as the arithmetic mean of all the estimates made by the team members during this first round, without the need to perform further rounds of estimation
upvoted 0 times
...
...
Cecilia
1 months ago
I prefer option B, let's go with the most frequent estimate value
upvoted 0 times
...
Gladys
1 months ago
I'm not sure, I think option A could also be a valid approach
upvoted 0 times
...
Kati
1 months ago
This is why we have planning poker, to hash out the differences and come to a consensus. Let's dive in and discuss further.
upvoted 0 times
...
Emogene
1 months ago
Hmm, I'm not convinced by the majority vote on 3 story points. We should consider all the estimates before making a decision.
upvoted 0 times
Hubert
15 days ago
Let's hear from Memb4 and Memb6 about their choices before moving on.
upvoted 0 times
...
Melvin
21 days ago
I agree, we should take into account all the estimates before deciding.
upvoted 0 times
...
...
Zack
1 months ago
I agree with Esteban, 3 story points doesn't seem right. Let's hear from Memb4 and Memb6 to get a better understanding of the task.
upvoted 0 times
...
Esteban
1 months ago
3 story points? That's way too low, we need to revisit this and get a more accurate estimate.
upvoted 0 times
Ira
7 days ago
We need to ensure we have a clear understanding before finalizing the estimate.
upvoted 0 times
...
Georgene
13 days ago
Maybe there was a misunderstanding in the user story that led to the discrepancy.
upvoted 0 times
...
Ria
22 days ago
I agree, let's hear their reasoning before moving on to the next round.
upvoted 0 times
...
Barbra
30 days ago
We should discuss why Memb4 and Memb6 chose such different estimates.
upvoted 0 times
...
...
Xenia
1 months ago
I agree with Quentin, it's important to discuss the reasons behind the extreme estimates
upvoted 0 times
...
Quentin
2 months ago
I think we should go with option D
upvoted 0 times
...

Save Cancel