You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.

At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.

Which of the following statements is true in this context?

K4 3 credits

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Detra
1 days ago
I think we should start system testing when all requirements are frozen.