The Grid is comprised of all single members. Which member will upgrade first?

Show Suggested Answer Hide Answer
Suggested Answer: A

Comprehensive and Detailed In-Depth

Upgrading a Grid of single members (no HA pairs):

A: Admins define Upgrade Groups or schedules (Grid > Upgrade), choosing the order (e.g., ''Member1 first''). Correct.

B: GM typically upgrades last by default to maintain control, but this can be overridden. Incorrect.

C: Reporting server (if present) has no priority---user-defined. Incorrect.

D: GMC upgrades only if promoted, not inherently first. Incorrect.

Practical Example: In an INE lab, schedule Member2 first, test upgrade, and troubleshoot sequence issues.