IIBA Exam CCBA Topic 4 Question 21 Discussion

Actual exam question for IIBA's CCBA exam
Question #: 21
Topic #: 4
[All CCBA Questions]

Which stakeholder in the solution assessment task will provide information on technical constraints that could limit the solutions that may be implemented?

Show Suggested Answer Hide Answer
Suggested Answer: D

Operational support can provide information on technical constraints that may limit the solutions that can be implemented.

Answer, B is incorrect. Suppliers provide information on the functionality associated with a particular solution option.

Answer, C is incorrect. The sponsor approves the expenditure of resources to purchase or develop a solution and approve the final recommendation.

Answer, A is incorrect. The project manager plans and manages the selection process of the solution.