IIA Exam IIA-CIA-Part3 Topic 4 Question 59 Discussion

Actual exam question for IIA's IIA-CIA-Part3 exam
Question #: 59
Topic #: 4
[All IIA-CIA-Part3 Questions]

A organization finalized a contract in which a vendor is expected to design, procure, and construct a power substation for $3,000,000. In this scenario, the organization agreed to which of the following types of contracts?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!