When a facility manager initiates an office relocation project, which item is completed first?
The project charter is the first step in initiating any office relocation project. It serves as the formal authorization that outlines:
Project scope -- Defines what is included/excluded.
Objectives -- Establishes the purpose and expected outcomes.
Key stakeholders -- Identifies project sponsors, decision-makers, and involved teams.
Preliminary timeline and budget -- Provides a high-level cost estimate and schedule.
Without a project charter, there is no official approval or framework for developing the program, securing budgets, or signing new leases.