Which two statuses of a Purchase Order will allow a receipt of new items to be processed in the Receiving application if the Purchase Order is not being revised?

Show Suggested Answer Hide Answer
Suggested Answer: A, C

In IBM Maximo Manage, if a Purchase Order is not being revised, two statuses that will allow a receipt of new items to be processed in the Receiving application are APPR and INPRG.