Refer to the Exhibit.

An engineer has attempted to configure two pairs of switches m the referenced configuration it Is required to implement

Multi-Chassis Link Aggregation for each pair of switches

The ports of the Aruba 8325 switches used for Agg01 and Agg02 are populated as follows

The configuration includes:

There is an error message stating "mismatched group speed" What should you add to the configuration to correct the error?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Tamar
6 days ago
I think the correct answer is C) 'speed 10-full' under interfaces 1/1/12 and 1/1/13.