A customer is moving a server from a co-location facility back into their existing data center to comply with new internal policies on data management

Due to budget constraints, the customer cannot purchase any additional switches and will need to use an existing end-of-row design with HPE FlexFabric switches While the server will be installed six racks away from the switches, the total cable run with cable management Is expected to be 35 m.

Which component should be selected when designing the 10 Gbps connectivity option for the server?

Show Suggested Answer Hide Answer
Suggested Answer: A