Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

HP Exam HPE0-S22 Topic 2 Question 13 Discussion

Actual exam question for HP's HPE0-S22 exam
Question #: 13
Topic #: 2
[All HPE0-S22 Questions]

A customer requires a server infrastructure update for its Hadoop HBase solution. The HBase maximum

dataset size will be 120TB.

To host HBase, the architect is planning three HPE Moonshot 1500 chassis fully populated with cartridges.

The populated chassis provide the following in total:

- 135 processors with four 2.9GHz cores each

- 4.23TB RAM

- 64.8TB local storage on SSDs

An aspect of the design is under provisioned and is likely to cause performance to degrade to one-tenth or even one-hundredth of its potential.

How can the architect resolve this problem?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel