MultipleChoice
You work as a project manager for company Inc. You do not want to change the task relationship, but you require a 'waiting time' before the starting of the activity can begin. Which of the following is the best approach to alleviate this issue?
OptionsMultipleChoice
Which of the following techniques is described in the statement below? "It is an early warning project management tool that allows managers to discover and control errors before they become unmanageable."
OptionsMultipleChoice
Which of the following describes the statement below? "It allocates continuous monitoring of the schedule, permits the project manager to track the critical activities, and alerts the project manager to the possibility that non-critical activities may be delayed beyond their total float, thus creating a new critical path and delaying project completion."
Options