Which of the following are inputs of the Control Scope process? Each correct answer represents a complete solution. Choose all that apply.
You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
Which of the following are inputs of the Control Scope process? Each correct answer represents a complete solution. Choose all that apply.
You work as a project manager for company Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?
Kallie
26 days agoHubert
1 months agoAdelaide
2 months agoGlory
2 months agoDorcas
3 months agoKiera
3 months agoCherelle
3 months agoTwana
4 months agoShayne
4 months agoInocencia
4 months agoWeldon
4 months agoCeleste
5 months agoShizue
5 months agoJenise
5 months agoRikki
5 months agoQueen
5 months agoYun
6 months agoNakita
6 months agoErick
7 months agoJillian
8 months agoChristoper
8 months ago