Which of the following are inputs of the Control Scope process? Each correct answer represents a complete solution. Choose all that apply.
You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
Which of the following are inputs of the Control Scope process? Each correct answer represents a complete solution. Choose all that apply.
You work as a project manager for company Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?
Hubert
1 days agoAdelaide
23 days agoGlory
1 months agoDorcas
2 months agoKiera
2 months agoCherelle
2 months agoTwana
3 months agoShayne
3 months agoInocencia
3 months agoWeldon
3 months agoCeleste
4 months agoShizue
4 months agoJenise
4 months agoRikki
4 months agoQueen
4 months agoYun
5 months agoNakita
5 months agoErick
6 months agoJillian
7 months agoChristoper
7 months ago