Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GIAC Exam GISF Topic 3 Question 51 Discussion

Actual exam question for GIAC's GISF exam
Question #: 51
Topic #: 3
[All GISF Questions]

The executive team wants you to track labor costs for your project as well as progress on task

completion and the resulting dates. What information must you update for tasks to provide this

information?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Emilio
2 days ago
I think the answer is D) Actual Start, Percent Complete, and Remaining Duration because it provides a comprehensive view of labor costs and progress.
upvoted 0 times
...
Paul
3 days ago
I disagree, I believe the answer is A) Start, Work, and Remaining Work.
upvoted 0 times
...
Edgar
6 days ago
I think the answer is C) Actual Start, Actual Work, and Remaining Work.
upvoted 0 times
...

Save Cancel