Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GIAC Exam GCPM Topic 8 Question 42 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 42
Topic #: 8
[All GCPM Questions]

You work as a project manager for company Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Viva
6 months ago
That gives us a cost performance index of 362,250 / 430,000 = 0.84, so the correct answer should be D) 0.84.
upvoted 0 times
...
Pete
6 months ago
I agree with In. The formula for cost performance index is EV/AC.
upvoted 0 times
...
Lucy
6 months ago
So, if we plug in the numbers, EV is $805,000 x 45% = $362,250, and AC is $430,000.
upvoted 0 times
...
In
6 months ago
I think the cost performance index should be calculated as the ratio of earned value to actual cost.
upvoted 0 times
...
Juan
6 months ago
I think it will be 0.84 based on how much of the budget we've actually used.
upvoted 0 times
...
Linn
6 months ago
I agree with 0.87 seems like the correct value.
upvoted 0 times
...
Wade
7 months ago
I believe it will be 0.80 because we spent more than planned.
upvoted 0 times
...
Val
7 months ago
I think the cost performance index will be 0.87.
upvoted 0 times
...
Jamika
8 months ago
Alright, let's do this! Budgeted Cost of Work Performed = 45% of $805,000 = $362,250. Actual Cost of Work Performed = $430,000. CPI = $362,250 / $430,000 = 0.84.
upvoted 0 times
...
Barrett
8 months ago
CPI = Budgeted Cost of Work Performed / Actual Cost of Work Performed. So we need to calculate those values first.
upvoted 0 times
...
Denny
8 months ago
Hold on, how did you arrive at that? I'm still trying to wrap my head around the formula for CPI.
upvoted 0 times
Katina
6 months ago
Yeah, the correct answer is D) 0.84.
upvoted 0 times
...
Frank
6 months ago
So, CPI = $362,250 / $430,000 which equals 0.84.
upvoted 0 times
...
Nancey
6 months ago
And the actual cost is $430,000.
upvoted 0 times
...
Jaime
7 months ago
We know the earned value is $805,000 * 0.45 which is $362,250.
upvoted 0 times
...
Frank
7 months ago
So for this project, we need to use the formula CIP = EV / AC.
upvoted 0 times
...
Katina
7 months ago
To calculate CPI, you divide the earned value by the actual cost.
upvoted 0 times
...
...
Daniel
8 months ago
I'm leaning towards option C, 0.86. That seems to make the most sense based on the information provided.
upvoted 0 times
...
Naomi
8 months ago
Okay, let's think this through step-by-step. We've got the budget, the percentage of work completed, and the actual amount spent. Shouldn't be too hard to figure out the cost performance index.
upvoted 0 times
...
Ilda
8 months ago
Wow, this question seems tricky! I'm not sure I'm fully prepared for this kind of calculation in the exam.
upvoted 0 times
...

Save Cancel