Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GIAC Exam GCPM Topic 5 Question 61 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 61
Topic #: 5
[All GCPM Questions]

You work as a project manager for company Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Paola
1 months ago
Oof, these cost performance index questions always get me. But I'm pretty sure the answer is A. I mean, 0.87 just has a nice ring to it, don't you think? It's like a fine wine – smooth and sophisticated.
upvoted 0 times
Aleta
10 days ago
I agree with you, I also think it's C) 0.86. Let's go with that.
upvoted 0 times
...
Micaela
27 days ago
I think the answer is actually C) 0.86. It's a close call, but that's my pick.
upvoted 0 times
...
...
Ricki
1 months ago
Ah, the ol' cost performance index question. I'm feeling lucky, so I'm gonna go with D. Hey, if it's good enough for the local casino, it's good enough for me!
upvoted 0 times
Nadine
3 days ago
D) 0.84
upvoted 0 times
...
Shenika
6 days ago
C) 0.86
upvoted 0 times
...
Ashlee
10 days ago
B) 0.80
upvoted 0 times
...
Annabelle
11 days ago
A) 0.87
upvoted 0 times
...
...
Ma
2 months ago
I'm going with C. The math just seems to work out better for that option, and I don't want to overthink this. Besides, who doesn't love a good 0.86 every now and then, am I right?
upvoted 0 times
Shad
27 days ago
I agree with you, C) 0.86 seems like the best option. Let's go with that.
upvoted 0 times
...
Emerson
1 months ago
I'm leaning towards D) 0.84. It just feels like the right answer to me.
upvoted 0 times
...
Elinore
1 months ago
I think I'll go with A) 0.87. It seems like the most logical choice based on the numbers.
upvoted 0 times
...
...
Stanford
2 months ago
Hmm, let's see... I think the correct answer is B. The project has spent $430,000 out of a $805,000 budget, and it's 45% complete. So the cost performance index should be 0.80, which is option B.
upvoted 0 times
Micah
1 months ago
Yes, the project's cost performance index is 0.80.
upvoted 0 times
...
Ronny
1 months ago
That makes sense, option B) 0.80 seems to be the right choice.
upvoted 0 times
...
Herman
2 months ago
I agree, the cost performance index should be 0.80.
upvoted 0 times
...
Tayna
2 months ago
I believe the correct answer is B) 0.80.
upvoted 0 times
...
...
Chauncey
2 months ago
I agree with Nan, 0.87 makes more sense since we are ahead of schedule in terms of project completion.
upvoted 0 times
...
Nan
2 months ago
I disagree, I believe it will be 0.87 because we have completed 45 percent of the project work.
upvoted 0 times
...
Denny
2 months ago
I think the cost performance index will be 0.86.
upvoted 0 times
...

Save Cancel