Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25%
- Ends In
00:00:00
Coupon code:
SAVE25
X
Welcome to Pass4Success
Login
|
Sign up
-
Free
Preparation Discussions
Mail Us
support@pass4success.com
Location
US
MENU
Home
Popular vendors
Salesforce
Microsoft
Nutanix
Amazon
Google
CompTIA
SAP
VMware
Fortinet
PeopleCert
Eccouncil
HP
Palo Alto Networks
Adobe
ServiceNow
Dell EMC
CheckPoint
Linux Foundation
Discount Deals
New
About
Contact
Login
Sign up
Home
Discussions
GIAC Discussions
Exam GCPM Topic 5 Question 58 Discussion
GIAC Exam GCPM Topic 5 Question 58 Discussion
Actual exam question for GIAC's GCPM exam
Question #: 58
Topic #: 5
[All GCPM Questions]
Which of the following statements describes the critical path?
A
It is the shortest path in the project network diagram.
B
It cannot be crashed.
C
It is always one path with the longest duration.
D
It shows the project's earliest date for completion.
Show Suggested Answer
Hide Answer
Suggested Answer:
D
by
Roxane
at
Sep 19, 2024, 03:48 PM
Limited Time Offer
25%
Off
Get Premium GCPM Questions as Interactive Web-Based Practice Test or PDF
Contribute your Thoughts:
Submit
Cancel
Pearline
2 months ago
If the critical path was the shortest, we'd all be out of a job! C is the way to go.
upvoted
0
times
...
Leonard
2 months ago
The critical path is like the superhighway of your project - it's the one you can't afford to mess with!
upvoted
0
times
...
Odette
2 months ago
The critical path shows the project's earliest completion date, so D is the right answer. Easy peasy!
upvoted
0
times
Mozell
10 days ago
Oh, I see. Thanks for clarifying!
upvoted
0
times
...
Diane
21 days ago
Actually, it's D) It shows the project's earliest date for completion.
upvoted
0
times
...
Karima
25 days ago
No, I believe it's C) It is always one path with the longest duration.
upvoted
0
times
...
Josefa
1 months ago
I think it's A) It is the shortest path in the project network diagram.
upvoted
0
times
...
...
Tayna
2 months ago
Hmm, I'm not sure if the critical path can be 'crashed' or not. I'll go with C just to be safe.
upvoted
0
times
...
Lawanda
2 months ago
Definitely C, the critical path is always the longest path in the project network diagram.
upvoted
0
times
Danica
23 days ago
I believe it's D, the critical path shows the project's earliest date for completion.
upvoted
0
times
...
Staci
24 days ago
I think it's A, the critical path is the shortest path in the project network diagram.
upvoted
0
times
...
...
Delsie
2 months ago
I think the critical path is the one with the longest duration, so C seems to be the correct answer.
upvoted
0
times
Leeann
1 months ago
Oh, I see. Thanks for clarifying that. I'll remember that for next time.
upvoted
0
times
...
Orville
1 months ago
Actually, the critical path is the shortest path in the project network diagram, so A is the correct answer.
upvoted
0
times
...
Keshia
2 months ago
I think the critical path is the one with the longest duration, so C seems to be the correct answer.
upvoted
0
times
...
...
Arlette
2 months ago
But doesn't it show the project's earliest date for completion?
upvoted
0
times
...
Latosha
3 months ago
I believe it is always one path with the longest duration.
upvoted
0
times
...
Arlette
3 months ago
I think the critical path is the shortest path in the project network diagram.
upvoted
0
times
...
Log in to Pass4Success
×
Sign in:
Forgot my password
Log in
Report Comment
×
Is the comment made by
USERNAME
spam or abusive?
Commenting
×
In order to participate in the comments you need to be logged-in.
You can
sign-up
or
login
Save
Cancel
Pearline
2 months agoLeonard
2 months agoOdette
2 months agoMozell
10 days agoDiane
21 days agoKarima
25 days agoJosefa
1 months agoTayna
2 months agoLawanda
2 months agoDanica
23 days agoStaci
24 days agoDelsie
2 months agoLeeann
1 months agoOrville
1 months agoKeshia
2 months agoArlette
2 months agoLatosha
3 months agoArlette
3 months ago