You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
Evan
4 months agoCorinne
4 months agoHaydee
5 months agoWalton
4 months agoLizbeth
4 months agoBenedict
4 months agoTran
5 months agoPhuong
5 months agoLashandra
4 months agoJenelle
4 months agoBrandon
4 months agoCharlette
4 months agoJade
5 months agoClarence
5 months agoJenifer
4 months agoAnglea
4 months agoFletcher
4 months agoCurtis
5 months ago