Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GIAC Exam GCPM Topic 3 Question 63 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 63
Topic #: 3
[All GCPM Questions]

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Oretha
11 days ago
I think the cost performance index should be less than 0.93.
upvoted 0 times
...

Save Cancel