Actual exam question for GIAC's GCPM exam
Question #: 43
Topic #: 3
[All GCPM Questions]

You are the project manager of a computer upgrade project. You and the vendor are in dispute over the deliverables the vendor was to provide and configure. What document can best describe how you and the vendor are to proceed if there is a claim against the vendor?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Gracie
6 months ago
I think the contract takes precedence in this case because it specifically details the agreement between the project manager and the vendor.
upvoted 0 times
...
Lon
7 months ago
But isn't the procurement management plan also important in this situation?
upvoted 0 times
...
Titus
7 months ago
I agree with User 1. The contract should outline the responsibilities and clauses for disputes.
upvoted 0 times
...
Ernestine
7 months ago
I think the document that can best describe how to proceed with a claim against the vendor is the contract.
upvoted 0 times
...
Cristy
8 months ago
So we should refer to the contract for guidance.
upvoted 0 times
...
Denise
8 months ago
The document that describes how to proceed in case of a claim is the contract.