Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GIAC Exam GCPM Topic 1 Question 41 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 41
Topic #: 1
[All GCPM Questions]

Marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which could cause the project to be late by more than a month. Marsha does not want this risk event to happen so she devises extra project activities to ensure that the risk event will not happen. The extra steps, however, will cost the project an additional $10,000. What type of risk response is this approach?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Kimbery
6 months ago
I believe it's still mitigation, as she's trying to reduce the impact of the risk rather than increase the opportunities.
upvoted 0 times
...
Jess
6 months ago
But wouldn't it be considered enhancing since she's adding extra activities to ensure the risk event doesn't happen?
upvoted 0 times
...
Fidelia
6 months ago
I agree with Leota, because Marsha is taking proactive steps to reduce the impact of the risk.
upvoted 0 times
...
Leota
6 months ago
I think the answer is A) Mitigation.
upvoted 0 times
...
Yesenia
6 months ago
I believe it's mitigation because Marsha is taking steps to reduce the impact of the risk event.
upvoted 0 times
...
Isabella
7 months ago
I'm not so sure, maybe it's enhancing the risk response.
upvoted 0 times
...
Jackie
7 months ago
I agree with Ronald, it definitely seems like mitigation.
upvoted 0 times
...
Ronald
7 months ago
I think this approach is mitigation.
upvoted 0 times
...

Save Cancel