Question #: 80
Topic #: 3
[All GE0-806 Questions]

An agent is scheduled to start a shift at 12:00 PM and the Start Before threshold is set to 5. Ifthe agent starts the shift at 11:54 AM. They will be considered________.

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Lai
6 months ago
So it seems we have mixed opinions on this question. We should review the guidelines to confirm the correct answer.
upvoted 0 times
...
Samuel
6 months ago
I also think it would be considered adherent, as long as they are within the threshold time.
upvoted 0 times
...
Ming
6 months ago
I'm not sure, but I think the correct answer is A) Adherent because they are within the threshold.
upvoted 0 times
...
Johanna
6 months ago
I think it would be considered an exception since it's only 6 minutes before the shift start time.
upvoted 0 times
...
Hildegarde
6 months ago
I disagree, I believe they would be considered severely non-adherent because they are starting before the threshold.
upvoted 0 times
...
Lai
7 months ago
I think if the agent starts at 11:54 AM, they will be considered adherent.
upvoted 0 times
...

Save Cancel