BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam PPM-001 Topic 7 Question 101 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 101
Topic #: 7
[All PPM-001 Questions]

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Salena
1 months ago
Hmm, that makes sense too. Fast tracking can free up contingency reserves for other uses.
upvoted 0 times
...
Penney
1 months ago
I disagree, I believe the answer is C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Salena
2 months ago
I think the answer is A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
Lisbeth
2 months ago
B? Really? Positive total float on the critical path? That's like saying unicorns are real. A is the only logical choice here.
upvoted 0 times
...
Stephane
2 months ago
Haha, look at these options. It's like they're trying to trick us! I'm going with A. Who wants to increase their risk of failure? Not this guy!
upvoted 0 times
Carin
22 days ago
Let's go with A then, better safe than sorry.
upvoted 0 times
...
Tina
23 days ago
I think B could also be a possibility, but A does make more sense.
upvoted 0 times
...
Chantay
1 months ago
I agree, A seems like the safest option.
upvoted 0 times
...
...
Annabelle
2 months ago
I'm not sure about that. I think C might be the right answer. Releasing contingency reserves sounds like a good way to deal with the compressed schedule.
upvoted 0 times
Cordell
26 days ago
D) Duration buffers are added to maintain a focus on planned activity durations.
upvoted 0 times
...
Keneth
29 days ago
C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Emerson
2 months ago
B) The critical path will have positive total float.
upvoted 0 times
...
Audria
2 months ago
A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
...
Tandra
2 months ago
A is definitely the correct answer. Fast tracking increases the risk of not finishing the project on time. That's just common sense.
upvoted 0 times
Fredric
1 months ago
Yes, it makes sense that fast tracking would increase the risk of not finishing on time.
upvoted 0 times
...
Rolande
1 months ago
I agree, A is the correct answer. Fast tracking definitely increases the risk.
upvoted 0 times
...
...

Save Cancel