GAQM Exam PPM-001 Topic 1 Question 5 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 5
Topic #: 1
[All PPM-001 Questions]

A project team member tells you that she went to her project manager with a good idea for a useful change to the project. Instead of giving her approval to make the change, the project manager asked her to write a report describing the benefits of the change. What is

the MOST appropriate advice for the situation?

Show Suggested Answer Hide Answer
Suggested Answer: C