Which of the following are product risks and which are project risks?
a.The navigation through some parts of the website may need to be different from others.
b.Sprint 1 may not be completed on time, leading to a delay to the start of Sprint 2.
c.Text versions of images may not always be possible.
d.There may be a need to buy a capture-replay tool for regression testing.
key member of the team may leave before the Sprints have been completed.