GAQM Exam CSM-001 Topic 2 Question 68 Discussion

Actual exam question for GAQM's CSM-001 exam
Question #: 68
Topic #: 2
[All CSM-001 Questions]

You are the Scrum Master and your Development Team of 6 members has completed six Sprints with thefollowing information:

Sprint 1: 10 pontos

Sprint 2: 11 pontos

Sprint 3: 15 pontos

Sprint 4: 14 pontos

Sprint 5: 15 pontos

Sprint 6: 10 pontos

The remaining story points for product development total 42. What is the approximate number ofSprintrequired to complete product development?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Shanda
4 months ago
So the answer is C) 4. Thanks for the calculation, team!
upvoted 0 times
...
Kindra
4 months ago
Since we have 42 points left, we will need approximately 4 Sprints to complete the product development.
upvoted 0 times
...
Dwight
5 months ago
So, the total points from all Sprints is 75. And the average points per Sprint is 12.5.
upvoted 0 times
...
Twana
6 months ago
I agree. Let's sum up the points from all Sprints and divide by the number of Sprints completed.
upvoted 0 times
...
Shanda
6 months ago
I think we can calculate the average points per Sprint first.
upvoted 0 times
...