Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam APM-001 Topic 1 Question 69 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 69
Topic #: 1
[All APM-001 Questions]

When cost variance is negative and schedule variance is positive, the project is:

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Catarina
3 months ago
This question is giving me a headache. Let's see, negative cost variance and positive schedule variance... Sounds like a classic case of 'how to confuse an entire project team.' I'll guess D, complete.
upvoted 0 times
...
Edmond
3 months ago
This is a real 'glass half empty, glass half full' situation. I'm going to go with C, on schedule. That way, the project manager can at least pretend everything is fine.
upvoted 0 times
Markus
2 months ago
C) on schedule.
upvoted 0 times
...
Derick
2 months ago
B) over budget and ahead of schedule.
upvoted 0 times
...
Laticia
2 months ago
A) under budget and behind schedule.
upvoted 0 times
...
...
Phung
3 months ago
Ah, the age-old question of project management Tetris. Clearly, the answer is A - under budget and behind schedule. That's the classic 'Murphy's Law' scenario.
upvoted 0 times
Kimberely
2 months ago
D) complete; all planned values have been earned.
upvoted 0 times
...
Jarod
2 months ago
C) on schedule.
upvoted 0 times
...
Carla
2 months ago
B) over budget and ahead of schedule.
upvoted 0 times
...
Galen
2 months ago
A) under budget and behind schedule.
upvoted 0 times
...
...
Zona
3 months ago
I think it's option A too, because the project is not meeting the planned schedule even though it's under budget.
upvoted 0 times
...
Bernardine
3 months ago
I agree with Gaynell, because cost variance being negative means we are spending less than planned, but schedule variance being positive means we are ahead of schedule.
upvoted 0 times
...
Kathryn
3 months ago
When I see negative cost variance and positive schedule variance, it's like the project is trying to do the hokey pokey - one foot in, one foot out. I'll go with B, over budget and ahead of schedule.
upvoted 0 times
Shantell
2 months ago
Sabina: Interesting perspectives, let's look into it further.
upvoted 0 times
...
Reuben
2 months ago
User 3: I'm not sure, but I think it might be C, on schedule.
upvoted 0 times
...
Sabina
3 months ago
User 2: I disagree, I believe it's B, over budget and ahead of schedule.
upvoted 0 times
...
Celeste
3 months ago
User 1: I think it's A, under budget and behind schedule.
upvoted 0 times
...
...
Gaynell
4 months ago
A) under budget and behind schedule.
upvoted 0 times
...

Save Cancel