New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam APM-001 Topic 1 Question 69 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 69
Topic #: 1
[All APM-001 Questions]

When cost variance is negative and schedule variance is positive, the project is:

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Zona
6 days ago
I think it's option A too, because the project is not meeting the planned schedule even though it's under budget.
upvoted 0 times
...
Bernardine
10 days ago
I agree with Gaynell, because cost variance being negative means we are spending less than planned, but schedule variance being positive means we are ahead of schedule.
upvoted 0 times
...
Kathryn
13 days ago
When I see negative cost variance and positive schedule variance, it's like the project is trying to do the hokey pokey - one foot in, one foot out. I'll go with B, over budget and ahead of schedule.
upvoted 0 times
...
Gaynell
23 days ago
A) under budget and behind schedule.
upvoted 0 times
...

Save Cancel