During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
The team member working on it estimates seven days.
What value (in days) should be used for planning?
Why does the Daily Scrum need to be held at the same location and time?
During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
The team member working on it estimates seven days.
What value (in days) should be used for planning?
Yuki
10 days agoDelbert
17 days agoLaura
23 days agoAnnita
1 months agoGail
2 months agoBea
2 months agoMendy
2 months agoSamira
2 months agoGeorgene
3 months agoTammara
3 months agoCeleste
3 months agoTenesha
3 months agoJillian
4 months agoGayla
4 months agoRebbeca
4 months agoCecil
4 months agoCarma
4 months agoRuthann
5 months agoNilsa
5 months agoAmber
5 months agoAlton
5 months agoHerminia
5 months agoLorrie
5 months agoSage
6 months agoDella
6 months agoWillodean
6 months agoErasmo
7 months agoPhuong
7 months agoDick
8 months agoCarmen
9 months agoLeatha
9 months ago