Exin Exam ITSM20F.EN Topic 4 Question 109 Discussion

Actual exam question for Exin's ITSM20F.EN exam
Question #: 109
Topic #: 4
[All ITSM20F.EN Questions]

What is the objective of the Continual Improvement (Act) stage of Planning and Implementing Service Management, as described in the ISO/IEC 20000 standard?

Show Suggested Answer Hide Answer
Suggested Answer: B

A . Incorrect. This is not relevant.

B . Correct. This is part of the standard.

C . Incorrect. Documenting these documents is part of Do, revising is part of Act (in de PDCAmethodology). This is no part of the proposals for new or changed services.

D . Incorrect. This plan is much broader than only new or changed services.